Project Description

Contracted With: Tioga Electric
General Contractor: Killian Construction
Schedule: January 2009 completed August 2009

Project Size

  • 6 floors, 150 rooms (Courtyard)
  • 3 floors, 47 rooms, 18 suites (Fairfield)
  • 1,100 Cables
  • $110,000 contract
  • 1,390 Man-hours
  • Crew size average 8-12 at peak